Tank Installation

  • Installation of a 24,000 gallon flat bottom FRP tank in place of an existing 20,000 gallon skirted tank
  • Initial contract was awarded to another Engineering firm whose design indicated installation would take 4-5 days to complete
  • This tank stored material that was a main additive for 90 percent of their products, which meant a substantial loss of production if removed from service for 5 days
  • Client requested M&K’s services to evaluate the design and procedure
  • M&K’s proposal was a 24-hour design and install procedure
  • M&K was hired to redesign and install the tank. Project was completed with M&K’s design and installed in less than 24 hours.