New Reactor on 3rd Floor of Building

  • Schedule- driven project requiring less than 5 days shut down to the main production line
  • Installation through the roof was estimated at 14 days
  • Total install time 3 days. Schedule was met by using mid air transfer to thread the reactor through a 2nd floor opening, and setting it on the 3rd floor. Tank design and installation sequence was coordinated through our Lead Construction Manager.
  • M&K’s design and construction skills saved 11 days of potential downtime for the client