Compressor Installation

  • Installation of (2) Hydrogen Compressors next to an existing compressor while in operation
  • Job criteria was to limit down time with our design
  • 40 foot modularized pipe bridge was designed and delivered with all piping installed
  • Compressors purchased as skid units
  • Tie-ins were designed and located to be completely installed in less than 14 hours
  • Cooling water lines were live tapped to prevent shut down in other sections of the plant
  • Project was turned over to production 2 weeks prior to scheduled completion