Addition to Existing Plant

  • 10 million dollar capital project
  • Parallel Design with R&D, Manufacturing, Engineering Design and Construction taking place simultaneously
  • 100 pieces of equipment with over 10,000 feet of welded SS pipe and 5,000 feet of Carbon steel
  • Addition of floor for installation of a new 12,000 gal reactor inside an existing building which was still in operation
  • Accelerated schedule to pour concrete and set pipe bridges within a 30-day time period
  • Original estimated completion date reduced by 3 months allowing the first batch of product to be made before original scheduled milestone.
  • By using our construction managers, total construction time was 4 months. Total time from receiving lab data to project completion was less than 12 months