Client Name Professional Services Capital Costs
ATP Engineering, Design for Water Project $5 million
Membrane system for the advance oxidation of a waste stream. In involved operation at high pressure. All phases of design were included.
Gulf Coast Waste Engineering Design, Project Management $6 million
Disposal authority & support for Bayport Oxygen Injection Project. This design is highly proprietary. M&K had responsibility for all phases of the design.
ISP Engineering Design, Project Management for over 100 jobs In excess of $10 million
M&K has a permanent presence in the Texas plant. We handle all the projects for ISP, which have ranged from several million dollars to as small as one thousand. All of this work is confidential.
Lonza, Inc. Engineering, Design, Project Management for Overflow Storage Tank $2 million
Installation of a reactor in an existing building. Design and construction supervision were primary responsibilities. Installation of reactor took three cranes — one 200 ton, one 300 ton, and a tailing crane — and involved a mid-air transfer. Reactor design during the preceding 18 months was instrumental in the installation.

Addition to existing plant:

  • 10 million dollar capital improvement project.
  • Parallel Design with R&D, Manufacturing, Engineering Design and Construction going on simultaneously.
  • 100 pieces of equipment with over 10,000 feet of welded SS pipe and 5,000 feet of Carbon steel.
  • Addition of floor for installation of a new 12,000 gal reactor inside an existing building that was still in operation.
  • Poured concrete and set pipe bridges starting on August 15 and by September 15 were laying pipe.
  • Original estimated completion date cut by 3 months with the first batch of product made before Christmas.
  • Total Construction time by using our construction managers was 4 months, with total time from receiving the Lab data to Project completion less than 12 months.

Hydrogen Compressors Installation:

  • Installation of 2 new hydrogen compressors next to an existing hydrogen compressor while ensuring plant could stay on-line.
  • Job criteria was to limit down time with our design.
  • A 40 foot pipe bridge was designed and delivered with all piping installed.
  • Compressors purchased as skid units.
  • Tie-ins were designed and located to be completely installed in less than 14 hours.
  • Cooling water lines were live tapped to prevent shutting down other sections of the plant.
  • With our design the project was turned over to production 2 weeks before scheduled completion.

New reactor installation on 3rd floor of existing building:

  • A simple installation except the plant wanted to limit shut down of the main production line for less than 5 days total.
  • The reactor was set by using a mid air transfer; threading it through a 2nd floor opening, and setting it on the 3rd floor.
  • Tank design and installation sequence was coordinated through our lead Construction Manager. Total time for this install was 3 days. Installing it through the roof was estimated at 14 days.
  • M&K design and construction skills saved 11 days of potential down time for the client.

Tank Installation:

  • Installed 24,000 gal flat bottom FRP tank in place of a existing 20,000 gal skirted tank.
  • Job criteria was to limit down time with our design.
  • This job was originally given to another engineering company. When the design was done the other engineering firm said that is would take 4 to 5 days to have the tank installed. This tank stored material that was a main additive for 90 percent of their products which meant a substantial loss of production if it was out of service for five days. M&K was called in to evaluate the design and procedure and informed the client that this could be done in less than 24 hours. M&K was then hired to redesign the Insulation of this tank and the installation procedure. The tank was installed in less than 24 hours.

Contrast Media Expansion:

  • Expansion of a X-ray contrast media plant. Involved design of a new centrifuge,
  • reactor system, and platform support. Involved validation and clean room work.
  • Handling of solvents was critical to the design.

Water Treatment Project:

  • Membrane system for the advanced oxidation of a waste stream. It involved
  • operation at high pressure. All phases of design were included.

Project Management for over 100 projects:

  • M&K has a permanent presence in a large Texas chemical plant. We handle all of the projects which have ranged from several million dollars to a small as one thousand. All of this work is confidential.

Other M&K Selected Projects

  • Phosphonates and Amines process Development, Design Plant Expansion, Construction Supervision and Startup.
  • Petrochemical Plant Vapor Recovery Process Design, Detailed Design Supervision, Construction Supervision and Startup (multiple systems).
  • Multipurpose Specialty Organic Plant for Mallinckrodt Chemical.
  • Pyridine Dicarboxylic Acid Process Development, Design, Construction Supervision and Startup.
  • Permanganate Plant Process Development, Design, Construction Supervision and Startup.
  • Cesium Chemicals Plant (99.999% Purity) Process Development, Design, Construction, Supervision and Startup.
  • Fumaric Acid process Development, Design, Construction, Supervision and Startup (Chairman of the Board Award)
  • Special Pharmaceutical Process Development, Design, Pilot Testing and Startup Supervision.

We are not the largest in town, but we get the job done early and for cost. So the next time you have any chemical plant issues remember M&K Engineering.